The Standing Committee of the Provincial Party Committee conducted a field inspection of the implementation progress of two key projects.
Provincial Party Secretary Nguyen Khac
Than led the inspection team. Also participating were the Standing Deputy
Provincial Party Secretary and Chairman of the Provincial People's Council
Hoang Nghia Hieu; the Deputy Provincial Party Secretary and Chairman of the
Provincial People's Committee Vo Trong Hai; and leaders of relevant departments
and agencies.
Provincial Party Secretary Nguyen Khac Than, along
with other members of the Provincial Party Standing Committee, inspect the
progress of the Quynh Lap LNG Thermal Power Plant project in Tan Mai ward.
Provincial Party Secretary Nguyen Khac Than and other members of the
Provincial Party Standing Committee inspect the progress of the Quynh Lap LNG
Thermal Power Plant project in Tan Mai ward. Photo: Pham Bang.
The project includes a thermal power plant with a
capacity of 1,500MW (comprising two 750MW units); and an LNG storage facility
with a tank capacity of approximately 250,000m³.3 and the LNG
reprocessing system; the Quỳnh Lập LNG Thermal Power Plant's dedicated port has
one liquid/gas berth capable of handling 1.5 million tons of cargo and a
synchronized technical infrastructure system.
The
total land and sea area is approximately 67.28 hectares (excluding the ship
turning area and the common breakwater of the Dong Hoi Port area), of which
57.29 hectares are land and 9.99 hectares are sea and coastline.
The project has a total investment of approximately
VND 55,946 billion (equivalent to USD 2.11 billion). This project is included
in the list of national key projects and priority projects in the energy
sector. The target schedule is to begin commercial operation of Unit 1 in 2029
and complete the entire project by 2030.
The Standing Committee of the Provincial Party
Committee, the Executive Committee of the Provincial Party Committee, and the
Provincial Party Committee have met and unanimously approved the policy for the
Quynh Lap LNG Thermal Power Plant project.”The project has an urgent need for
immediate implementation to ensure completion according to the revised Power
Development Plan VIII and the revised Power Development Plan VII implementation
plan, providing a legal basis for applying the investor selection method in
special circumstances.”
At its 35th session, the Provincial People's Council
passed a Resolution identifying the Quynh Lap LNG Thermal Power Plant project
as an urgent project requiring immediate implementation to ensure completion
according to the schedule and requirements of the revised Power Development
Plan VIII and the Implementation Plan for the revised Power Development Plan
VIII.
Upon completion, the project will generate electricity
from liquefied natural gas (LNG), transmitting it from the production site to
the distribution system; contributing to a stable power supply for the national
grid and meeting the energy needs of businesses.
The project will also meet environmental criteria,
contributing to the reduction of greenhouse gas emissions that impact the
environment. It will promote economic growth in Nghe An province by attracting
investment capital for industrial production, shifting the economic structure,
and increasing the proportion of industrial growth in the province in the
coming period.
The project has a total investment of approximately 55,946 billion VND
(equivalent to 2.11 billion USD)
After conducting a field inspection and listening to
reports, Provincial Party Secretary Nguyen Khac Than emphasized that this is an
important project with a driving force and ripple effect, and upon completion,
it will make a significant contribution to the province's development.
Therefore, the comrade requested the Provincial
People's Committee to work with the strategic investment partner to finalize
the project implementation schedule. The approval of the investment policy for
the project must be completed by December 2025.
The Provincial Party Secretary also requested that
departments and agencies focus on expediting investment procedures and actively
resolving any obstacles that may arise. Tan Mai Ward was instructed to
strengthen propaganda and mobilization efforts to help residents understand the
purpose and importance of the project, thereby gaining their consent to hand
over the land for its implementation.
Provincial Party Secretary Nguyen Khac Than requests that all levels,
sectors, and localities be determined and resolute in order to commence the
project by April 30, 2026.
In addition, Tan Mai ward must now quickly implement
procedures for compensation, land clearance, and the construction of
resettlement areas for the people. "All levels, sectors, and localities
must be determined and resolute so that the project can be started by April 30,
2026," Provincial Party Secretary Nguyen Khac Than stated.
Following that, Provincial Party Secretary Nguyen Khac
Than and other members of the Provincial Party Standing Committee inspected the
progress of the Cua Lo deep-water port construction and operation investment
project in Hai Loc commune.
Provincial Party Secretary Nguyen Khac Than and other
members of the Provincial Party Standing Committee inspected the progress of
the Cua Lo deep-water port construction and operation project in Hai Loc
commune.
The project is invested by the International Transport
Development Investment Joint Stock Company (ITID). To date, the project has
full legal basis, having received an investment certificate in 2010 and an
amendment in 2021; completed the basic design, and received approval for the
Environmental Impact Assessment Report, feasibility study report, detailed
planning at a scale of 1/500, construction drawings, and cost estimates.
Land clearance work has been completed, with land
records extracted for 10/18.76 hectares; surveying and confirmation by
residents completed for 8.76/18.76 hectares; and land valuation completed for
10 hectares. The approval of the compensation and land clearance plan is
expected to be completed in January 2026.
According to the investor's proposed project
adjustments, Phase 1 will involve the construction of general cargo, container,
and bulk cargo berths No. 6 and No. 7, each 500m long and capable of handling
50,000 DWT vessels; an access bridge approximately 3,320m long; connecting
bridge No. 1, 270m long; and the port's hinterland area. Phase 2 will involve
the construction of general cargo, container, and bulk cargo berth No. 5, 300m
long and capable of handling 100,000 DWT vessels; connecting bridge No. 2,
86.5m long; and the port's hinterland area.
The investor also proposed adjusting the land area of
the port's hinterland to 32 hectares, and the water surface area to 150
hectares. They also proposed adjusting the total investment capital to VND
7,394 billion and revising the project implementation schedule to complete
piers No. 6 and 7 in Q4/2028; and complete pier No. 5 in Q4/2030.
The proposal suggests adjusting the project to include
the bridge connecting National Highway 7C to Cua Lo Port, allowing investors to
undertake the project themselves. It also proposes separating the 1,550m long
breakwater from the main project, making it an independent project to be
developed under the Build-Transfer (BT) model.
The project will commence on the morning of December
19, 2025, along with other large-scale and significant projects and works
nationwide on December 19 - National Resistance Day, to celebrate the 14th
National Congress of the Party.
Provincial Party Secretary Nguyen Khac Than requested
the investor to focus resources, manpower, equipment, and machinery to
accelerate construction progress, striving to put all three berths No. 7, 6,
and 5 into operation in 2027.
After conducting a site inspection and listening to
reports, Provincial Party Secretary Nguyen Khac Than emphasized that this is an
important infrastructure project for the province. Therefore, he requested the
investor to focus resources, manpower, equipment, and machinery to accelerate
construction progress, striving to have all three berths (numbers 7, 6, and 5)
operational by 2027. He also urged Hai Loc commune to expedite land clearance
to hand over the land to the investor.
Appreciating the value and effectiveness of the
project once it becomes operational, Provincial Party Secretary Nguyen Khac
Than suggested that relevant departments study and develop a comprehensive plan
for the fisheries infrastructure area, integrated with the deep-water port, to
fully exploit the value the port brings and thereby increase income for the
people.
Source: baonghean.vn (December 16, 2025)