The Provincial People's Committee has approved the investment policy and the investor for the construction and operation of infrastructure in Zone B of Tho Loc Industrial Park
The Nghe An Provincial People’s Committee issued
Decision No. 56/QD-UBND dated June 16, 2026, approving the investment policy
and simultaneously approving the investors for the project on construction and
business of infrastructure for Zone B of Tho Loc Industrial Park.
The project
aims to invest in the construction and operation of industrial park
infrastructure and is located in Tan Chau commune, within the Southeast Nghe An
Economic Zone. The project covers an area of approximately 174.65 hectares,
with a total estimated investment capital of around 2,138,628,086,000 VND. Of this, the investors’ contributed capital
is 320,794,213,000 VND, while
mobilized capital accounts for 1,817,833,873,000
VND. The project has a duration of 50 years from the date of the first
land allocation or land lease by the State.
According
to the Decision, the two approved investors are: Pacific Group Joint Stock
Company (headquartered at 9th Floor, No. 25 Ly Thuong Kiet Street, Cua Nam
Ward, Hoan Kiem District, Hanoi); Japan Construction Management Joint Stock
Company (headquartered at 15th Floor, VCCI Tower, No. 9 Dao Duy Anh Street,
Dong Da District, Hanoi).
The project
will be implemented in two phases:
Phase 1
(100 hectares): The preparation period runs from Q1/2025 to Q4/2026.
Compensation, site clearance, and land handover will take place from Q1/2027 to
Q3/2027. Construction and commissioning are scheduled from Q3/2027 to Q4/2028.
Phase 2
(74.65 hectares): Site clearance and land handover will be carried out from
Q3/2028 to Q1/2029. Construction and commissioning will take place from Q1/2029
to Q2/2030.
The
Provincial People’s Committee assigned the People’s Committee of Tan Chau
commune to take the lead and coordinate with relevant departments and agencies
to guide the investors in implementing the project. The commune is responsible
for determining land origin, land classification, and land users; proposing
plans for the relocation or restoration of affected structures; and allocating
the entire compensation budget for the affected Diễn Phú Commune Kindergarten
(former) to build a new kindergarten. The commune is also responsible for
monitoring project operation and submitting quarterly reports on implementation
progress to the Department of Finance and the Southeast Nghe An Economic Zone
Authority.
For the
investors, the Provincial People’s Committee requires full legal responsibility
for the accuracy of submitted documents; proper and sufficient contribution of
committed charter capital; and completion of all legal procedures (land,
construction, environment, fire prevention and fighting, etc.) before project
implementation.
During
implementation, the investors must strictly comply with legal regulations on
the protection of irrigation works, ensure no negative impact on the lives and
production activities of surrounding residents, promptly report any discovery
of relics, antiques, or valuable minerals, and fulfill deposit obligations to
guarantee project execution.
The
Province also requires that the project reserve at least 5 hectares of
industrial land (or at least 3% of total industrial land area) for lease to
small and medium-sized enterprises, supporting industries, and
innovation-driven enterprises. The investors and relevant agencies are also
responsible for proactively updating clearance boundaries and site demarcation
milestones for the North–South Expressway section from Dien Chau to Bai Vot and
the North–South high-speed railway project to ensure compliance with safety
corridor regulations.